Tuesday, July 21, 2009

- FRAMING AND MORE DELIVERIES
21st July, 2009

Tonight we headed down to the site again. The frame including the most of the roofing is all pretty much complete bar some tie down's and a few little niche sections here and there. The windows and sliding doors have been delivered to site along with the gutters and fascias.

The 31,500 litre concrete water tank is now in the ground also. It will just need some backfill around it and then it will be approx 400mm out of the ground.