Thursday, July 30, 2009

- UPDATE
30th July, 2009

A drive down tonight after dinner and we have noted the following changes:

  1. - Internal plumbing fit off's for water and also gas are in for the kitchen, laundry and bathrooms.
  2. - We have the external taps :)
  3. - Electrical rough in is all complete
  4. - Plumbing return lines into water tank are complete
  5. - Our Seaforth bricks have arrived. This is exciting... 15 pallets worth
  6. - All windows and sliding doors are installed.

Can't wait now till the weekend to grab some pictures... Be back Soon !!