ALMOST THERE...HANDOVER ANNOUNCED !
18th September, 2009


Well our build has been going so amazingly fast that it has literally been
too hard to keep the blog updated constantly. So here we are a little under a month from the last post. Since then...heaps has happened... read on

We also found out today that handover will be on the 9th October with a walk through on the 1st. Yippeee

Week from 24th Aug to 28th Aug
Wet Area tiling completed, Pre Paint inside, Downpipes attached, all external field gullies, drainage points etc all attached.

Week from 1st Sep to 4th Sept
Ridge pointing on roof done, internal paint first coats, Stone bench tops in bathrooms, vanity basins in, kitchen sink in, front entrance door sent back to Corinthian to be swapped over.

Week from 7th Sep to 11th Sep
Kitchen appliances delivered and some fitted later in week, Electrical fit off, ceiling fans, network cabling, Tap fittings, baths installed, garage door in, glass splashback in, wire racking in linens etc, water tank monitoring system in.

Week from 14th Sep till today..
Mirrors installed, Pre paint outside, gas pipe work in, Gas Stove installed, hot water system connected, fireplace installed and roof insulation in.

Now some pics so far .. click pics for larger version

























2 comments:

  1. I love your kitchen... it's near identical to mine in colour selections! (No bias)

    ReplyDelete
  2. you managed your Tile designing beautifully. I am building with M3tricon in Tampa by Clearwater Real Estate
    and they allow up to 600*600 porcelain (upgrade cost).

    ReplyDelete